| Catholic Parish Outreach (CPO) Facility Move Project Plan - As of 09/25/08 | ||||||||
| Task | Task | Due | Actual | Comments/ | ||||
| Task # | Task Description | Owner | Dependency | Date | Date | Status | Critical Path Item | |
| ADMINISTRATIVE | ||||||||
| 1 | Signing of Lease for facility 2013 Raleigh Blvd. | Rick | done | |||||
| 2 | Landlord to provide a LOI | Rick | done | |||||
| 2 | Secure the construction contractor - Clancy & Theys | Rick | done | Project Lead - Evan Sturm | ||||
| 3 | Secure the plumbing contractor | Rick | done | |||||
| 3.A | Secure a service provider for Sprinkler system | Rick | ||||||
| 4 | Secure the Electrical contractor | Rick | done | |||||
| 5 | Secure the HVAC contractor | Rick | done | |||||
| 6 | Secure the Architect | Rick | done | |||||
| 6.A | Initial architect drawing 4/4/08 | Greg/Paul | done | |||||
| 6.B | Final architect drawing 4/25/08 | Greg/Paul | done | |||||
| 7 | Acquire town building permits | done | ||||||
| 7.A | Contact city of Raleigh to wave the Express costs for permits | Rick | done | |||||
| 8 | Identify all handicap areas that need to be addressed | Rick | done | Landlord will assume the cost to implement | ||||
| 9 | Define our current lease/move date | Rick | done | On or before 9/01/08 | ||||
| 10 | Coordinate w/ Urban Ministries to provide support during move | Rick | ||||||
| 11 | Furniture, fixture, equipment inventory | Jay/Ben | done | |||||
| 11.A | Furniture acquisition - Desks, chairs, book shelves and lamps | Terry/Jay | ||||||
| 12 | Publicize move - agencies/churches & flyer in grocery bags | Marge Consuelo | ||||||
| 13 | Develop a publicity plan | Rick/Res. Comm. | ||||||
| 14 | Organize and schedule an open house event | Marge Consuelo | scheduled for 11/20 | |||||
| 15 | Alarm system - possible upgrade | Rick | TBD | |||||
| 16 | Contact transportation to determine where to place the benches | Terry | done | benches will have top removed | ||||
| 17 | Contact Bob Schantz for potential office furn. | Jay | N/A | |||||
| 18 | Walk through current facility to determine repairs | Terry | done | |||||
| 18.A | Implement repairs at current facility as per landlord | Terry | ||||||
| 19 | Finalize who will sub-lease part of warehouse area | Rick | done | |||||
| 20 | Review with Progress Energy the potential of reduced rates based on Off Peak Vs On Peak | Jay | TBD | |||||
| 21 | Install intercom system | TBD | N/A | |||||
| 22 | Equipment estimated costs - cooler, pallet jacks, Refrig. & phone system | Don/Marty | done | |||||
| 23 | Identify the project sub-committee members | Rick | done | |||||
| 23.A | Warehouse and Food Re-packing areas | Don | done | |||||
| 23.B | Clothing area | Charlotte | done | |||||
| 23.C | Securing office Furn. & Installation of Phone System, Computer Network and Activation Security System | Jay | done | |||||
| 23.D | Publicity, Planning Open House and Marketing | Rick/Res. Comm. | done | |||||
| done | ||||||||
| 23.E | Moving process current and new facility | Jim/Jay | ||||||
| 24 | Establish weekly project status meetings with sub-committees | Rick | done | |||||
| 25 | Contact Delta Comm to acquire a copy of current contract - James Turner 800-239-3000, W-277-7160, C749-8481 | Jay | ||||||
| 26 | Provide Jay with technology consultant contact #, Albert | Rick | done | |||||
| 27 | Create the CPO outside sign and coordinate with the vendor | Jay | done | Mike Chapman sign unlimited will move the current sign | ||||
| 28 | Contact NSI, Inc. Chris Mangino to review future ISP/Telecomm. Service provider options | Jay | done | meeting held on 9/26 | ||||
| 29 | Removal of bus stop bench tops | Terry | ||||||
| 30 | Advise cost of (50) charis and (4) small desks | Jay | ||||||
| Construction - Waiting, Reception, Office & Clothing Areas | ||||||||
| 50 | Men's bathroom move the stall wall to allow for handicap req. | Evan | ||||||
| 51 | Ladies bathroom move the stall wall to allow for handicap | Evan | ||||||
| 52 | Create a new handicap unisex bathroom where current mop sink area is | Evan | ||||||
| 55 | Install (1) wall to split (1) current office into (2) rooms | Evan | ||||||
| 57 | Build a 5' foot wall to divide clothing & reception area to end 3' prior to end of wood floor | Evan | ||||||
| 58 | Install chair-rail in lobyy and reception areas | Evan | ||||||
| 59 | Install windows in all offices that support interviews | Evan | ||||||
| 60 | Purchase chairs for waiting areas | Terry | ||||||
| 61 | Purchase a cart for the Clothing area | Terry | ||||||
| 62 | Remove glass door in reception area | Evan | ||||||
| 65 | Install (2) TV's in front reception and waiting areas | |||||||
| 66 | Install door near bathrooms in hall and warehouse | Evan | ||||||
| 67 | Cloths closet install shelves for equipment | |||||||
| 68 | Install in Terry's office a second door | Evan | ||||||
| 69 | Install a front door buzzer | TBD | ||||||
| 71 | Need to have clothing rack disks under legs | |||||||
| 72 | Office furniture planning | Terry/Jay | ||||||
| 72.A | Waiting area | Terry/Jay | ||||||
| 72.B | reception area | Terry/Jay | ||||||
| 72.C | Classroom | Terry/Jay | ||||||
| 72.D | Administrative offices | Terry/Jay | ||||||
| 72.E | Contact State Surplus Furniture and other vendors to determine costs and purchase | Terry/Jay | ||||||
| 72.F | Determine the wall hanging themes throughout there facility | Terry/Jay | ||||||
| 73 | Review options for a wall Hanging | Marge | done | |||||
| 74 | Determine if we have (10) required operating fire extinguishes, and/or purchases what is needed | Terry | ||||||
| 75 | Determine existing speaker system if operating and capabilities | Jay | ||||||
| 76 | Install cabling for TV/VCR in hall closet | TBD | ||||||
| Construction Process - Classroom Area | ||||||||
| 102 | Construct a wall across the classroom with a 10' or 12' pocket door | Evan | ||||||
| 103 | Purchase furnishings for all classroom areas (Wake Tech a possibility) | TBD | ||||||
| Construction Process - Food Re-Packing Area | ||||||||
| 150 | Drop ceiling to a standard height | Evan | ||||||
| 151 | Lower the current sprinkler system | Leave the current sprinkler system and tap into it for new sprinklers in the food pack area | ||||||
| 152 | Install dish washer sink | TBD | ||||||
| 153 | Install a counter | TBD | ||||||
| 154 | Install cabinetry above the sink area | TBD | ||||||
| 155 | Determine if floors will be painted or vinyl tiles | Rick | done | tile to be installed | ||||
| 156 | Install floor coverings | TBD | ||||||
| 157 | Install large vegetable sink | TBD | ||||||
| 158 | Install mop sink underneath dish washer sink | TBD | ||||||
| 159 | purchase stainless steel table | TBD | ||||||
| Construction Process - Warehouse Area | ||||||||
| 200 | Coordinate Install storage rack mounting shelf system | Don | ||||||
| 201 | Purchase powered pallet jack | done | ||||||
| 201.A | Power pallet needs to be reapired | Don | ||||||
| 202 | move eyewash station to front of warehouse close to batteries, or purchase portable eyewash station | |||||||
| 203 | Install new freezer/cooler | Don | done | |||||
| 204 | Purchase a scale | |||||||
| 205 | Install power, phone, and LAN in back warehouse corner for sub-lease | ABS | ||||||
| 206 | De-install ceiling lights and leave fixtures | |||||||
| 207 | Install ceiling lights in freezer/cooler | Don | ||||||
| 208 | Install 'air curtain' in freezer/cooler doors | Don | ||||||
| 209 | Coordinate with the electrician the electrical requirements for freezer/cooler | Don | ||||||
| 210 | Installation of walk threads and door curtain | Don | ||||||
| 211 | Install back-up camera for truck | Marty | ||||||
| Renovation Process - Exterior of Facility | ||||||||
| 250 | Install a metal rail the length of the current dock to end at the delivery area | done | ||||||
| 251 | Remove shrubs along the handicap walk way | done | ||||||
| 252 | Install a hand rail if required along the handicap walk way | done | ||||||
| 253 | Install decking in front of the area where the (3) dumpsters will be req. | Evan | ||||||
| 254 | Paint lines for parking spaces | TBD | ||||||
| 255 | Add a 3rd handicap parking spot | TBD | ||||||
| 256 | Create a parking lot space (2) for food pick up | TBD | ||||||
| 257 | Back exterior install a glass door | TBD | TBD | |||||
| 258 | Determine if we can expand the parking area with gravel stone base | Rick | TBD | |||||
| 259 | Identify exterior lighting needs i.e. back parking | TBD | ||||||
| 259 | Advise Clancy & Theys of the CPO sign requirements electrical, emergency switch & timer switch | Jay | done | |||||
| Carpenter Requirements | ||||||||
| 300 | Back area counter (blue top) add shelves above and cabinet below | TBD | ||||||
| Electrical & HVAC | ||||||||
| 350 | Install HVAC requirements in the food re-packing area | Landlord | done | |||||
| 351 | Electrical outlets for refrigerators and freezers in food re-packing area | Evan | ||||||
| 352 | Electrical outlets in the warehouse as needed | Evan | ||||||
| 353 | Install an A/C vent in the computer room | Evan | ||||||
| Plumbing | ||||||||
| 400 | Install sink drains in the food re-packing area for 2 sinks and a mop sink | Evan | ||||||
| 401 | Install mop sink | Evan | ||||||
| 402 | Install a unisex handicap bathroom (1) toilet and (1) hand sink | Evan | ||||||
| Technology, Telecommunications & Alarm Systems | ||||||||
| 360 | Develop an I.T. infrastructure plan (network) | Tom | ||||||
| 360.A | Assessment of current system, Needs & GAPS | Tom | ||||||
| 360.B | Design/development of implementation process & plan with timelines | Tom | ||||||
| 360.C | Network requirements determine wireless and/or cable | Tom | done | Network will be cabled Vs Wireless | ||||
| 360.D | Outline equipment requirements of desk top, network, printers, routers Etc. | Tom | ||||||
| 360.E | Outline technology costs one-time and ongoing | Tom | ||||||
| 361 | Telecomm system selected and service provider is American Business Systems (ABS) | Marty | done | |||||
| 361.A | Contact Delta Comm. to review move requirements, costs and timeline, and current contract terms | Jay | DeltaComm will continue to provide service until contract expiration | |||||
| 361.B | Develop Telecomm implementation plan | Marty | ||||||
| 361.C | Acquire (3) system bids for costing | Marty | done | |||||
| 362 | Access current Alarm system | Rick | ||||||
| 362.A | Fire Alarm system | Rick | ||||||
| 362.B | Security Alarm system | Rick | ||||||
| 363 | Determine future options for ISP/Telecomm service providers, options and cost with NSI | Jay | TBD | |||||
| 364 | Coordinate the installation of Network/Telecomm. Cabling with ABS | Tom Derick | ||||||
| 365 | Coordinate installation of Telecomm system with ABS | Marty | done | |||||
| 366 | Identify the current cables that can be removed and advise Clancy & Theys | Tom | done | all current cables removed | ||||
| 367 | Install network cable jacks (terminations) | Derrick | ||||||
| Moving Process - Old to New Facility | ||||||||
| Key Milestones | ||||||||