CPO – Facility Move Project: Task & Resolution Log

 



 

ID #

Description of Task

Criticality/Priority

Owner

Resolution & Next Steps

Target

Date to Resolve

 Status

001

Signing of the facility lease

Critical

Rick

 

4/01/08

 

002

Develop the facility architectural design

Critical

Paul Stafford

 

4/01/08

 

003

Define the HVAC requirements, costs] and contractor

Priority

Rick

 

4/15/08

 

004

Secure the town building permits needed (where applicable)

Priority

TBD

 

TBD