CPO
– Facility Move Project: Task & Resolution Log |
ID # |
Description of Task |
Criticality/Priority |
Owner |
Resolution & Next Steps |
TargetDate to Resolve |
Status |
001 |
Signing of the facility
lease
|
Critical |
Rick |
|
4/01/08 |
|
002 |
Develop the facility
architectural design
|
Critical |
Paul Stafford |
|
4/01/08 |
|
003 |
Define the HVAC
requirements, costs] and contractor
|
Priority |
Rick |
|
4/15/08 |
|
004 |
Secure the town
building permits needed (where applicable)
|
Priority |
TBD |
|
TBD |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|